Community sample question for phased implementation
community-implementation-methods-001 · mcq_single · 1 mark
Source: Community submission by Example Contributor
Question
A school replaces its old student portal one year group at a time. Year 12 is moved first, followed by Year 11, then the junior years.
Which implementation method is being used?
Options
Reveal answer
C. Phased
Marking rubric
| Marks | Description |
|---|---|
| 1 | Identifies the correct implementation method. |
Explanation
This is phased implementation because the system is introduced in stages across groups.